Roadmap for TimeSeriesChart Implementation
This issue defines the logical order of implementation for the time series visualization components. Following this order will allow us to progressively build functionality while maintaining a usable component at each stage.
Implementation Order:
-
Base TimeSeriesChart (Issue #26) - PRIORITY 1
- Implementation of the base component with D3.js
- Fundamental structure on which everything else will be built
- Estimate: 25-30 hours
-
Downsampling and Data Aggregation (Issue #28) - PRIORITY 2
- LTTB algorithm and aggregation functions for handling massive datasets
- Will enable working with large datasets from the beginning
- Estimate: 25-34 hours
-
Zoom and Brushing (Issue #27) - PRIORITY 3
- Interactive functionality to explore specific time ranges
- Integrates with downsampling to maintain performance
- Estimate: 18-27 hours
-
API Integration (Issue #29) - PRIORITY 4
- Connection with real data sources and zoom/brush-based loading
- State management and basic caching
- Estimate: 19-27 hours
-
UI and User Experience (Issue #30) - PRIORITY 5
- Tooltips, controls, and visual indicators
- General interface improvements
- Estimate: 17-24 hours
-
Performance Optimization (Issue #31) - PRIORITY 6
- Final optimizations for performance with massive datasets
- Done at the end when a functional component already exists
- Estimate: 20-28 hours
Total Estimated Time
- 104-139 hours (approximately 13-17 work days)
Considerations
Roadmap for TimeSeriesChart Implementation
This issue defines the logical order of implementation for the time series visualization components. Following this order will allow us to progressively build functionality while maintaining a usable component at each stage.
Implementation Order:
Base TimeSeriesChart (Issue #26) - PRIORITY 1
Downsampling and Data Aggregation (Issue #28) - PRIORITY 2
Zoom and Brushing (Issue #27) - PRIORITY 3
API Integration (Issue #29) - PRIORITY 4
UI and User Experience (Issue #30) - PRIORITY 5
Performance Optimization (Issue #31) - PRIORITY 6
Total Estimated Time
Considerations